For a client in North Dakota, we installed 20 piles under two separate concrete slabs to lift them back to their proper level after concrete caissons failed. Due to the amount of suction the caissons created, 20 Ton jacks were used at all pier locations to break the suction and lift the slabs. The mounting brackets were then attached to the footing and backfilled.